On the 3rd of August 2020 was scheduled the first major lifting for Ana Platform Project build in GSP Shipyard.
The lifting of approximately 127 tons Cellar Deck was performed in accordance with the documentation prepared by Blue Line engineers.
Advanced analysis with the finite element method using FEMAP NASTRAN SOFTWARE was performed to verify the stress and displacement that occurred in deck structure and lifting pad eyed in order to minimize the impact of lifting on local structure.
It was also prepared the set of two cranes LR1300 and LR1280 involved in lifting, using Liebherr Crane planer, the selection of lifting slings, and the design of pad eyes.
The lifting was performed in good conditions and the Cellar Deck was positioned on topside grillage as it was planned.